Helical Screw Pile Installation for a Solar Panel – Pro Post Foundations – Part 2



Our team successfully installed a screw pile foundation to put a solar panel for Natural Forces Solar in Nova Scotia. Here is an aerial video from our latest project. Another rocky site, we are excavating about 4 feet to get past a layer of rock, then screwing the piers in. Excellent torque values and acceptable depths. Project engineer has been on site and approves of our techniques – minimum depth of 6’ otherwise he wants to implement a grout solution with anything less. Galvanization took less than 4 days. We dropped the shipment on Monday afternoon last week and it was ready Friday morning.

adminHelical Screw Pile Installation for a Solar Panel – Pro Post Foundations – Part 2